Ghana’s Parliamentary Select Committee Parliamentary Select Committee on Agriculture and Cocoa Affairs visits Pwalugu project

0
1148
Ghana’s Parliamentary Select Committee Parliamentary Select Committee on Agriculture and Cocoa Affairs visits Pwalugu project

Ghana’s Parliamentary Select Committee on Agriculture and Cocoa Affairs has conceded the need to push government to show financial commitment towards the construction of the $404, 857, 414.06 Pwalugu Multi-Purpose Dam and Irrigation Project (PMDIP).

Both sides in the committee hailed President Nana Addo Dankwa Akufo-Addo, for the bold step taken to initiate the commencement of the project, which was on the national drawing board for about five decades.

The Committee, led by its chairman, Mr John Osei Frimpong, Member of Parliament for Abirem, reiterated the need for government to source funding for the project to come into fruition. The dam will serve relieving needs of the citizens of northern Ghana.

He described the Pwalugu project as a game changer, at Nalerigu, the North East Regional capital and said it would address relevant perennial problems of food stocks in the country, and especially make Northern Ghana the new food basket base, in Ghana’s quest to enhance all year round food production, food security and food sustainability.

Work schedules

The project which had 48 months to be executed, was behind schedule and after almost 24 months of sod-cutting to commence the Multipurpose Dam, the pace at which work was progressing was discouraging, adding that there was the need for the committee to advise government to source alternative funding to streamline work progression to meet deadlines per work schedules on the project.

Mr Frimpong said the Committee’s meeting was an extension of Parliament and was in the region to solicit information at first hand to see way forward for the construction of the multipurpose project, which he said was dear to the heart of Ghanaians.

The GNA gathered that only about $11,949, 052 was advanced to the contractor, PowerChina International Group Ltd, to execute capital plan under the project, out of estimated $55,939,719.26, thereby delaying the project from its scheduled plan.

President Nana Akufo-Addo cut the sod on November 29, 2019, to commence work on the Pwalugu Multi-Purpose Dam and Irrigation Project (PMDIP), one of the flagship Projects of the Government of Ghana.

The Project has three major components of power generation, irrigation and flood control.The Volta River Authority (VRA) and Ministry of Energy is responsible for the power generation and flood control while the Ministry for Food and Agriculture (MOFA) through the Ghana Irrigation Development Authority (GIDA) is responsible for the Irrigation component.

The irrigation component is expected to unlock the agricultural potential of the Savannah zone and to become the largest irrigation scheme in Ghana. The Chief Executive Officer of the Ghana Irrigation Development Authority (GIDA), Mr Wilson Kwabena Darkwah, said the project was justified and approved, with MPs as part of the approving agency, adding, it would take care of flood excesses to protect property, open bigger avenues for employment, and sustain all year round farming to discourage youth from the area from migrating down south.